Modular Building Schedule - Example
Listed below you will find a Pinecrest Modular Homes Building Schedule: Please note that most often tasks are occurring simultaneously. The number of days giving to a specific task has been estimated for scheduling purposes.
Engagement and Design
Collection of Engagement Fee
Finalize plans and develop estimate with Client
Sign contract
Sign off on All Plans and Proposal
Submit plans for state approval
Review and Finalize Factory Sales Order
Sign and File Subcontractor Proposals
Secure Building Permit
Receive Permit
Have house plotted on survey
Receive State Approval Letter
Order Insurance Certificates
Utilities
Electric
RFQ Electrician
Confirm Electrician
Apply for New Electrical Service
Turn on new Power Service
Receive Electrical Underwriter's Certificate
Finish Electrical
Finish Electrical Tie ins
Wire Boiler
"Prepare phone, cable and data for final connection"
Final Electrical Inspection
Plumbing
RFQ Plumber
Confirm Plumber
Receive Final Plumbing Certificate
Finish Plumbing
Complete Plumbing Tie ins
Install Boiler and HW Heater
Final Plumbing Inspection
Oil
Schedule Oil Delivery
Gas
Apply for New Gas Service
Perform pressure test
Call for line installation
Water
Apply for Water to Site
Trench for Water Line
Inspect Water Line Installation
Turn on Water Service
Receive Tap Letter
Site Work
Demolition
Secure Demolition Permit
Demolish structures on site
Erosion Control Measures
Clear and strip topsoil
Install Septic / Tie In to Sewer
Septic Excavation
Septic Installation
Receive Septic Certificate / Sewer Connect Letter
Install Retaining Wall
Install Drywells
Final Grading
Foundation
Certify Foundation Plan
RFQ Foundation
Excavate for foundations
Pour Footings
Footing Inspection
Pour Walls
Cure basement walls
Backfill foundation
Set Sill Plates w/ Copper Flashing
Waterproof/insulate basement walls
Perform foundation inspection
Pour Basement floor
Pour Garage Floor
Insulation
Fabrication and Delivery
Confirm On-Line Date
Confirmed Delivery Date
Confirm Staging Area
Confirm Driver's Contact Info
Confirm Road Permits 1
Set
Reserve Crane
Confirm Crane
"Order Set Supplies (tarps, lumber, nails)"
Order Dumpster
Set Boxes
Bolt Boxes
Hurricane Strapping
Install Temp Stairs
Exterior Finish
Siding
RFQ Siding
Confirm Sider
Side and Finish House
Soffits / Fascia
Roofer
RFQ Roofer
Confirm Roofer
Install and Finish Roof
Gutters and Leaders
Garage Doors
Portico / Decks
HVAC
Order HVAC Equipment
Install HVAC Equipment
Install Ductwork
Install Condesing Units
Finish HVAC
Interior Finishes
Install 1st floor shiploose items
Install 2nd floor shiploose items
General Carpentry
Finished Carpentry
Finish Seams
Tape and spackle 1st floor drywall
Tape and spackle 2nd floor drywall
Trim work
Painting -Touch up w/ builder's prime
Stairs and Rails
RFQ Stairs and Rails
Confirm Stairs and Rails
Finish Flooring
"Tile entry, kitchen and baths"
Carpet 1st floor
Carpet 2nd floor
Certificate of Occupancy
Install appliances
Cleanup for occupancy
Complete final inspection for certificate of occupancy
Final Acceptance
Perform final walk-through inspection
Complete punch list items