    This is modular first and second story addition on the North Shore of Long Island. The demolition, underpinning, and site construction was extremely difficult. The unique and challenging modular design of the first and second floors including the porch area was an incredible accomplishment. I want to thank all people involved including the homeowners, the architect, and the entire staff at Pinecrest Modular Homes and Signature Building Systems. Jonathan Davidson President
Powered by TypePad

Modular Building Schedule - Example

January 31, 2008

Modular Building Schedule - Example

Listed below you will find a Pinecrest Modular Homes Building Schedule:  Please note that most often tasks are occurring simultaneously.  The number of days giving to a specific task has been estimated for scheduling purposes.

Engagement and Design 
Collection of Engagement Fee
Finalize plans and develop estimate with Client   
Sign contract   
Sign off on All Plans and Proposal   
Submit plans for state approval   
Review and Finalize Factory Sales Order   
Sign and File Subcontractor Proposals   
Secure Building Permit    
Receive Permit   
Have house plotted on survey   
Receive State Approval Letter   
Order Insurance Certificates   
Utilities   
Electric   
RFQ Electrician   
Confirm Electrician   
Apply for New Electrical Service   
Turn on new Power Service   
Receive Electrical Underwriter's Certificate   
Finish Electrical   
Finish Electrical Tie ins   
Wire Boiler   
"Prepare phone, cable and data for final connection"   
Final Electrical Inspection   
Plumbing   
RFQ Plumber   
Confirm Plumber   
Receive Final Plumbing Certificate   
Finish Plumbing   
Complete Plumbing Tie ins   
Install Boiler and HW Heater   
Final Plumbing Inspection   
Oil   
Schedule Oil Delivery   
Gas    
Apply for New Gas Service   
Perform pressure test   
Call for line installation   
Water   
Apply for Water to Site   
Trench for Water Line   
Inspect Water Line Installation   
Turn on Water Service   
Receive Tap Letter   
Site Work   
Demolition 
Secure Demolition Permit   
Demolish structures on site   
Erosion Control Measures   
Clear and strip topsoil   
Install Septic / Tie In to Sewer   
Septic Excavation   
Septic Installation   
Receive Septic Certificate / Sewer Connect Letter   
Install Retaining Wall   
Install Drywells   
Final Grading   
Foundation   
Certify Foundation Plan   
RFQ Foundation   
Excavate for foundations   
Pour Footings   
Footing Inspection   
Pour Walls   
Cure basement walls      
Backfill foundation   
Set Sill Plates w/ Copper Flashing   
Waterproof/insulate basement walls   
Perform foundation inspection   
Pour Basement floor   
Pour Garage Floor   
Insulation   
Fabrication and Delivery   
Confirm On-Line Date   
Confirmed Delivery Date   
Confirm Staging Area   
Confirm Driver's Contact Info   
Confirm Road Permits    1
Set    
Reserve Crane   
Confirm Crane   
"Order Set Supplies (tarps, lumber, nails)"   
Order Dumpster   
Set Boxes   
Bolt Boxes   
Hurricane Strapping   
Install Temp Stairs   
Exterior Finish   
Siding  
RFQ Siding   
Confirm Sider   
Side and Finish House 
Soffits / Fascia   
Roofer   
RFQ Roofer   
Confirm Roofer   
Install and Finish Roof   
Gutters and Leaders   
Garage Doors   
Portico / Decks   
HVAC   
Order HVAC Equipment   
Install HVAC Equipment   
Install Ductwork   
Install Condesing Units   
Finish HVAC   
Interior Finishes   
Install 1st floor shiploose items   
Install 2nd floor shiploose items   
General Carpentry   
Finished Carpentry   
Finish Seams   
Tape and spackle 1st floor drywall   
Tape and spackle 2nd floor drywall   
Trim work   
Painting -Touch up w/ builder's prime   
Stairs and Rails   
RFQ Stairs and Rails   
Confirm Stairs and Rails   
Finish Flooring   
"Tile entry, kitchen and baths"   
Carpet 1st floor   
Carpet 2nd floor   
Certificate of Occupancy   
Install appliances   
Cleanup for occupancy   
Complete final inspection for certificate of occupancy   
Final Acceptance   
Perform final walk-through inspection   
Complete punch list items   