    This is modular first and second story addition on the North Shore of Long Island. The demolition, underpinning, and site construction was extremely difficult. The unique and challenging modular design of the first and second floors including the porch area was an incredible accomplishment. I want to thank all people involved including the homeowners, the architect, and the entire staff at Pinecrest Modular Homes and Signature Building Systems. Jonathan Davidson President
Powered by TypePad

Modular Construction Task List

February 01, 2008

Modular Construction-Task List

Land and Lot selection
    a. Evaluate site for modular accessibility
    b. Do a perk test if necessary
    c. Verify that the survey has been updated within the last two years

Design - Choose or create a modular a custom modular design. After a design concept has been agreed upon the design will be engineered and converted into building plans for permitting purposes. The plans will include floor plans, elevations, specifications, options, electrical, plumbing and sections. It will also included all the necessary code calculations and Res Check.

File for Building Permit
    a. Building Permit
    b. Electrical Permit
    c. Plumbing Permit
    d. Health Department - when required
    e. Road and Highway - when required
    f. Environmental - DEC - when requires
    g. Application for gas or electric service
    h. Stake out underground utilities
    i. Stake out foundation and set first floor elevations

Site Work
    a. Excavate for foundation, septic and/or sewer.
    b. Pour footing and foundation
    c. Install termite shield, sill plates, strapping, beams, anchor bolts and columns.
    d. Install footing drains and basement stone if necessary or specified
    e. Install  tar waterproofing
    f. Verify dimensions, square and level
    g. Install fire stop 2 x 8 under center carry beam at marriage wall
    h. Install lally columns

Site Preparation

  • Temporary electrical service if necessary.
  • Create access road if necessary.
  • Schedule pay loader if required.
  • Schedule delivery, set crew and contingency date

Exterior Finishing

  1. Install basement windows
  2. Backfill foundation
  3. Complete siding, fascia, soffit, shutters
  4. Install chimney
  5. Install gutters and leaders
  6. Optional exterior finishes porches, decks, walk ways
  7. Install garage doors
  8. Rough (back blade) grading
  9. Exterior clean up

Interior Finishing

  1. Install on site insulation not included by factory
  2. Install basement stairs
  3. Flush up and bolt all ceiling beams as required
  4. Remove temporary supports at mating walls
  5. Clamp and adjust marriage walls, install metal plates at doorways
  6. Cut and install filler strips for walls and floors
  7. Install interior stairs and rails
  8. Install and finish drywall
  9. Install interior doors and adjust
  10. Install attic stair trim and adjust stairs if necessary
  11. Complete baseboard and casement trim work
  12. Install finished flooring
  13. Install ship loose items left out to allow for electrical, plumbing, or flue access
  14. Blend Painting
  15. Install appliances

Electrical Completion

Plumbing Completion

HVAC Completion

Fireplace and Metalbestos Flues Completion

Closing

  1. Create and finish punch list
  2. Final clean up - removal of dumpster and toilet
  3. Final walk through with homeowner
  4. Issuance of Certificate of Occupancy
  5. Home owner occupancy